Florida SIRS & milestone inspection guide

A plain guide to the Florida milestone inspection and the structural integrity reserve study (SIRS): which buildings need them, when they are due, what the association must do with the results, and how to track the repairs.

Milestone inspection in Florida

Under Florida Statutes 553.899, a residential condominium or cooperative building three habitable stories or more must have a milestone inspection by December 31 of the year it reaches 30 years from its certificate of occupancy, and every 10 years after that. The local building official can move the first one to 25 years for buildings in harsh conditions, such as near salt water.

The inspection is done by a Florida licensed architect or engineer in two phases. Phase one is a visual inspection, due within 180 days after the association receives the building official's notice. If phase one finds substantial structural deterioration, a phase two inspection follows, which can include testing, and its progress report is due within 180 days of the phase one report. Repairs for substantial structural deterioration found in phase two must start within 365 days of the report.

Structural integrity reserve study (SIRS)

Florida Statutes 718.112(2)(g) requires a residential condominium association to have a SIRS at least every 10 years for each building three habitable stories or higher. The study must be done or verified by a licensed engineer or architect, or a certified reserve specialist or professional reserve analyst. It is based on a visual inspection, and the visual part of a milestone inspection done in the past 5 years can be used for it.

  • Items covered: roof, structure and load-bearing walls, fireproofing and fire protection, plumbing, electrical, waterproofing and exterior painting, windows and exterior doors.
  • Also covered: any other item with a deferred maintenance or replacement cost over $25,000 (or the division's inflation-adjusted amount) whose failure affects those items.
  • For each item: remaining useful life, replacement or deferred maintenance cost, and a reserve funding plan.
  • Associations existing on July 1, 2022 had to complete their first SIRS by December 31, 2025, or by December 31, 2026 if done with a milestone inspection due by then.

What the board has to do with the reports

  1. Within 14 days of the building official's notice, tell unit owners the milestone inspection is required and its deadline.
  2. Within 45 days of a milestone report, send owners the inspector's summary, post it on the property and on the association website if you must have one.
  3. Within 45 days of a SIRS, send owners a copy or a notice that it is available, and file the completion statement with the state division.
  4. Have an officer or director sign the affidavit acknowledging receipt of the SIRS.
  5. Fund reserves per the SIRS, and schedule the repairs each report lists.

Records to keep

Keep the sealed inspection reports, the SIRS, owner notices with the dates sent, contractor bids and disclosures, permits and the record of each repair: what was done, by whom, when and what it cost. The next milestone inspector and SIRS preparer will ask for this, and so will buyers' lenders and insurers.

Run it in Dovient Lite

Add each building and its major components, such as the roof, balconies, elevators and fire protection, as assets, and attach the milestone report and SIRS to the building's record. Open a work order for each repair the reports list, assign the contractor, and attach photos, invoices and permits as the work is done; the cost adds to each component. Set the next SIRS and milestone dates as yearly or every-N-years schedules, and export completed repairs as a PDF for the board and owners.

Start with Dovient Lite

Sources

Rules change and vary by state and county. Check the current text with your inspector or authority having jurisdiction. Last reviewed 2026-11-15.

Questions

What is the difference between a milestone inspection and a SIRS?
A milestone inspection checks whether the building is structurally safe, and is filed with the local building official. A SIRS estimates the remaining life and replacement cost of key components and sets how much the association must save in reserves.
Which Florida buildings need a milestone inspection?
Condominium and cooperative buildings three habitable stories or more, by December 31 of the year they turn 30 (or 25 where the local official requires it), and every 10 years after that.
How often is a SIRS required?
At least every 10 years for each condominium building three habitable stories or higher. An association can delay it for up to two budget years after a milestone inspection to focus funds on the repairs.
Does a SIRS apply to an HOA with single-family homes?
No. It applies to condominium buildings three stories or higher, not to single-family, duplex, triplex or fourplex dwellings with three or fewer habitable stories.